San Francisco / Mission / 1863 Mission St

1863 Mission St

37-unit 7-story residential project erect 7-story, 2 basements, 37 units condos for mix use building.

Complete37 UnitsAB 2011 MinisterialDBI Valuation $2.2M
Entitlement
Plan Check
Dec 2018
Awaiting Issuance
Dec 2018
Post-Issuance Addenda
Construction
Apr 2022
Complete
Apr 2022
Permit Filed
Mar 2006
Time in Active Review
11 months
excludes 142 months dormant
Completed
Apr 2022
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

December 2018

Permit issued on December 20, 2018. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeDecember 20, 2018
Key Milestones
Mar 2006
Permit Filed
New construction permit filed with DBI
Mar 2006
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2006
Dormant Period
No plan-check activity for ~6 months — applicant-side pause, not city queue time.
Oct 2006
Dormant Period
No plan-check activity for ~42 months — applicant-side pause, not city queue time.
Apr 2010
Dormant Period
No plan-check activity for ~94 months — applicant-side pause, not city queue time.
Dec 2018
Permit Issued
Construction can begin
Apr 2022
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Feb 2023
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 11 mo · Applicant: 0 mo · Dormant: 141 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Ajello Hoagland Linda.
In Review
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Ajello Hoagland Linda.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Finnegan John.
In Review
Mechanical (MECH)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau Danny.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Oct 2022
Construction startedJun 2019
Total inspections22
37 of 37 units certified for occupancy (Initial TCO, Apr 2022).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2023-02-21
106FINAL INSPECT/APPRVD
2023-02-21
106FINAL INSPECT/APPRVDPASSED
2022-10-17
145TCO ISSUEDPASSED
2021-10-25
142PRE-FINALPASSED
2021-06-18
142PRE-FINALPASSED
2020-05-26
126ROUGH FRAMEPASSED
2020-04-29
125ROUGH FRAME, PARTIALPASSED
2020-03-10
126ROUGH FRAMEPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.