Estimated Timeline
Permit issued — plan check completeJune 21, 2019
Key Milestones
Oct 2008
Permit Filed
New construction permit filed with DBI
Oct 2008
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2008
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
Jun 2009
Dormant Period
No plan-check activity for ~89 months — applicant-side pause, not city queue time.
Aug 2017
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Jun 2019
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 19 mo · Applicant: 0 mo · Dormant: 109 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Grob Carly.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Walls Mark.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Harshman Kjell.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Tom Bill.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Walls Mark.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.