Estimated Timeline
0 of 7 stations approved0% complete
Key Milestones
Jun 2014
Permit Filed
New construction permit filed with DBI
Jun 2014
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2014
Dormant Period
No plan-check activity for ~38 months — applicant-side pause, not city queue time.
Jan 2018
Dormant Period
No plan-check activity for ~16 months — applicant-side pause, not city queue time.
Mar 2020
Dormant Period
No plan-check activity for ~28 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Aug 2023
Currently Dormant
No plan-check activity for 1120 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 14 mo · Applicant: 1 mo · Dormant: 132 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Sucre Richard.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Kwok Stephen.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Tam Richard.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Luu Sarah.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.