Estimated Timeline
Permit issued — plan check completeMay 25, 2022
Key Milestones
Jun 2014
Permit Filed
New construction permit filed with DBI
Jun 2014
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2014
Dormant Period
No plan-check activity for ~35 months — applicant-side pause, not city queue time.
May 2017
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Jul 2018
Dormant Period
No plan-check activity for ~32 months — applicant-side pause, not city queue time.
May 2022
Permit Issued
Construction can begin
Mar 2025
Construction Complete
Certificate of occupancy issued
Mar 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Mar 2025
Certificate of Final Completion
CFC issued — all construction obligations met.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 19 mo · Applicant: 0 mo · Dormant: 76 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Sucre Richard.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Sucre Richard.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Chan Joseph.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Harshman Kjell.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Arriola Laura.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Casey Ryan.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Jan 2025
28 of 28 units certified for occupancy (CFC, Mar 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-03-07
106FINAL INSPECT/APPRVDPASSED
2025-01-07
142PRE-FINAL
2025-01-07
142PRE-FINALPASSED
2024-07-15
134OK TO COVERPASSED
2024-07-11
125ROUGH FRAME, PARTIALPASSED
2024-07-10
134OK TO COVERPASSED
2024-07-08
134OK TO COVER
2024-06-28
126ROUGH FRAMEPASSED