San Francisco / Castro/Upper Market / 2201 Market St

2201 Market St

20-unit 8-story residential project new construction of an 8 story building with 7 stories of 20 residentail dwelling units over commercial tenant spaces on the ground floor.

Dormant20 UnitsAB 2011 MinisterialDBI Valuation $2.0M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: Dormant — no activity for 180+ days. City desk: 23 mo · Applicant: 0 mo
Permit Filed
Oct 2014
Time in Active Review
23 months
excludes 94 months dormant
Review Stations
0 of 9
stations approved
Project Status
Dormant
Estimated Timeline

Permit Issuance Estimate

March 2027 — September 2027

Timeline driven by 5 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 9 unapproved stations
0 of 9 stations approved0% complete
Key Milestones
Oct 2014
Permit Filed
New construction permit filed with DBI
Oct 2014
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2014
Dormant Period
No plan-check activity for ~19 months — applicant-side pause, not city queue time.
Jul 2016
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Sep 2017
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
Jun 2018
Dormant Period
No plan-check activity for ~47 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Jul 2024
Currently Dormant
No plan-check activity for 773 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 23 mo · Applicant: 0 mo · Dormant: 119 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on August 23, 2023. 3 round(s) of review. Reviewer: Mcelroy Carey.
Comments Issued
Fire (SFFD)
SF Fire Department
Comments issued on July 15, 2024. 3 round(s) of review. Reviewer: Weiss-Ishai Sagiv.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on September 14, 2023. 4 round(s) of review. Reviewer: Chung Diana.
Comments Issued
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on July 07, 2023. 1 round(s) of review. Reviewer: Hoffman Daniel.
Comments Issued
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Comments issued on February 08, 2024. 1 round(s) of review. Reviewer: Casey Ryan.
Comments Issued
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Vu Doug.
In Review
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 4 cycle(s) to date. Reviewer: Choy Clinton.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Neighborhood Planning

Neighborhood Planning is the longest-running active review station on this project.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.