San Francisco / Castro/Upper Market / 2201 Market St

2201 Market St

20-unit 8-story residential project new construction of an 8 story building with 7 stories of 20 residentail dwelling units over commercial tenant spaces on the ground floor.

Permit Filed — In Plan Check20 UnitsAB 2011 Ministerial$2.0M Est. Cost
Permit Filed
Oct 2014
Active Review Since
Oct 2014
Review Stations
0 of 9
stations approved
Project Status
Filed
Estimated Timeline

Permit Issuance Estimate

November 2026 — May 2027

Timeline driven by 5 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 9 unapproved stations
0 of 9 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on August 23, 2023. 3 round(s) of review. Reviewer: Mcelroy Carey.
Comments Issued
Fire (SFFD)
SF Fire Department
Comments issued on July 15, 2024. 3 round(s) of review. Reviewer: Weiss-Ishai Sagiv.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on September 14, 2023. 4 round(s) of review. Reviewer: Chung Diana.
Comments Issued
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on July 07, 2023. 1 round(s) of review. Reviewer: Hoffman Daniel.
Comments Issued
Mental Health (HEALTH-MH)
Dept. of Public Health
Comments issued on February 08, 2024. 1 round(s) of review. Reviewer: Casey Ryan.
Comments Issued
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Vu Doug.
In Review
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 4 cycle(s) to date. Reviewer: Choy Clinton.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Neighborhood Planning

Neighborhood Planning is the longest-running active review station on this project.

Key Milestones
Oct 2014
Permit Filed
New construction permit filed with DBI
Oct 2014
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.