Estimated Timeline
Permit issued — plan check completeJanuary 02, 2019
Key Milestones
Feb 2015
Permit Filed
New construction permit filed with DBI
Feb 2015
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2015
Dormant Period
No plan-check activity for ~21 months — applicant-side pause, not city queue time.
Nov 2016
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Feb 2018
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Jan 2019
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 7 mo · Applicant: 0 mo · Dormant: 39 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Sucre Richard.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Cheung Derek.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
Mechanical (MECH)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lai Jeff.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Berona Marcus.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Gaime Berhane.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Wong Kendrick.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.