San Francisco / Mission / 3314 Cesar Chavez St

3314 Cesar Chavez St

57-unit 7-story residential project to erect 7 stories type 3a over 1a construction consisting of 57 covered multi-family residential dwelling units with 2 commercial units at ground floor, ove...

Dormant57 UnitsAB 2011 MinisterialDBI Valuation $8.0M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: Dormant — no activity for 180+ days. City desk: 19 mo · Applicant: 0 mo
Permit Filed
Apr 2015
Time in Active Review
19 months
excludes 80 months dormant
Review Stations
0 of 6
stations approved
Project Status
Dormant
Estimated Timeline

Permit Issuance Estimate

March 2027 — September 2027

No active review activity yet — estimate falls back to median durations for comparable SF projects of this size.

V0 empirical baselines from 6 unapproved stations
0 of 6 stations approved0% complete
Key Milestones
Apr 2015
Permit Filed
New construction permit filed with DBI
Apr 2015
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2015
Dormant Period
No plan-check activity for ~68 months — applicant-side pause, not city queue time.
Aug 2022
Dormant Period
No plan-check activity for ~12 months — applicant-side pause, not city queue time.
Aug 2023
Currently Dormant
No plan-check activity for 1120 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 19 mo · Applicant: 0 mo · Dormant: 117 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Liang Xinyu.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Mcelroy Carey.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Harshman Kjell.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Do Shannon.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.