Estimated Timeline
Permit issued — plan check completeFebruary 27, 2020
Key Milestones
May 2015
Permit Filed
New construction permit filed with DBI
May 2015
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2015
Dormant Period
No plan-check activity for ~17 months — applicant-side pause, not city queue time.
Dec 2016
Dormant Period
No plan-check activity for ~15 months — applicant-side pause, not city queue time.
Jan 2019
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Feb 2020
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 17 mo · Applicant: 0 mo · Dormant: 41 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Asbagh Claudine.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Asbagh Claudine.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Ospital Joseph.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Yu Eric.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Haney Tom.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.