Estimated Timeline
Permit issued — plan check completeJune 23, 2022
Key Milestones
May 2015
Permit Filed
New construction permit filed with DBI
May 2015
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2015
Dormant Period
No plan-check activity for ~26 months — applicant-side pause, not city queue time.
Jun 2018
Dormant Period
No plan-check activity for ~6 months — applicant-side pause, not city queue time.
Dec 2018
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Dec 2019
Dormant Period
No plan-check activity for ~14 months — applicant-side pause, not city queue time.
Nov 2021
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Jun 2022
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 25 mo · Applicant: 0 mo · Dormant: 60 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Ajello Hoagland Linda.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Ajello Hoagland Linda.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Harshman Kjell.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Wong Kendrick.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.