Estimated Timeline
1 of 7 stations approved14% complete
Key Milestones
Jul 2015
Permit Filed
New construction permit filed with DBI
Jul 2015
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2015
Dormant Period
No plan-check activity for ~43 months — applicant-side pause, not city queue time.
Apr 2020
Dormant Period
No plan-check activity for ~38 months — applicant-side pause, not city queue time.
Jun 2023
Dormant Period
No plan-check activity for ~28 months — applicant-side pause, not city queue time.
Nov 2025
Currently Dormant
No plan-check activity for 276 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 14 mo · Applicant: 2 mo · Dormant: 117 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Washington Delvin.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Tran Nancy.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Walls Mark.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Estrella Jerry.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Nguyen James.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved September 24, 2025. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.