Estimated Timeline
0 of 7 stations approved0% complete
Key Milestones
Aug 2015
Permit Filed
New construction permit filed with DBI
Aug 2015
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2015
Dormant Period
No plan-check activity for ~10 months — applicant-side pause, not city queue time.
Jul 2017
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Aug 2018
Dormant Period
No plan-check activity for ~6 months — applicant-side pause, not city queue time.
Mar 2019
Dormant Period
No plan-check activity for ~15 months — applicant-side pause, not city queue time.
Jun 2020
Currently Dormant
No plan-check activity for 2278 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 17 mo · Applicant: 0 mo · Dormant: 115 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Foster Nicholas.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Ospital Joseph.
Fire (SFFD)
SF Fire Department
Currently in review. 3 cycle(s) to date. Reviewer: Fasso Dominic.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Yu Eric.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 2 cycle(s) to date. Reviewer: Ossai Joseph.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.