Estimated Timeline
1 of 6 stations approved16% complete
Key Milestones
Oct 2015
Permit Filed
New construction permit filed with DBI
Nov 2015
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2016
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Dec 2017
Dormant Period
No plan-check activity for ~21 months — applicant-side pause, not city queue time.
Sep 2019
Dormant Period
No plan-check activity for ~49 months — applicant-side pause, not city queue time.
Feb 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Feb 2024
Currently Dormant
No plan-check activity for 931 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 16 mo · Applicant: 0 mo · Dormant: 113 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Walls Mark.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Stumpp Fred.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Zhou Andy.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Planning (CP-ZOC)
SF Planning Department
Approved February 05, 2024. Reviewer: Perry Andrew.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.