Estimated Timeline
Permit issued — plan check completeJanuary 10, 2020
Key Milestones
Dec 2015
Permit Filed
New construction permit filed with DBI
Jan 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2016
Dormant Period
No plan-check activity for ~12 months — applicant-side pause, not city queue time.
Mar 2018
Dormant Period
No plan-check activity for ~22 months — applicant-side pause, not city queue time.
Jan 2020
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 13 mo · Applicant: 0 mo · Dormant: 34 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Speirs Jeffrey.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Chan Joseph.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Priem Caroline.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.