San Francisco / Bayview Hunters Point / 6424 03Rd St

6424 03Rd St

17-unit 4-story residential project to erect 4 stories of 17 dwelling units with commercial on ground floor - maher ordinance - extended no.15513- required

Dormant17 UnitsAB 2011 MinisterialDBI Valuation $3.5M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: Dormant — no activity for 180+ days. City desk: 30 mo · Applicant: 0 mo
Permit Filed
Dec 2015
Time in Active Review
30 months
excludes 73 months dormant
Review Stations
4 of 9
stations approved
Project Status
Dormant
Estimated Timeline

Permit Issuance Estimate

March 2027 — September 2027

Timeline driven by 2 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 5 unapproved stations
4 of 9 stations approved44% complete
Key Milestones
Dec 2015
Permit Filed
New construction permit filed with DBI
Dec 2015
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2016
Dormant Period
No plan-check activity for ~73 months — applicant-side pause, not city queue time.
Aug 2024
Currently Dormant
No plan-check activity for 752 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 30 mo · Applicant: 0 mo · Dormant: 98 mo
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on August 05, 2024. 2 round(s) of review. Reviewer: Stacy Sara.
Comments Issued
Public Health (HEALTH)
Dept. of Public Health
Comments issued on May 15, 2024. 1 round(s) of review. Reviewer: Chen Bill.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Samonsky Ella.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Guzman Miguel.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Fire (SFFD)
SF Fire Department
Approved July 05, 2024. Reviewer: Ziegler Erik.
Approved
Building Code (BLDG)
Dept. of Building Inspection
Approved March 29, 2024. Reviewer: Mcelroy Carey.
Approved
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved April 11, 2024. Reviewer: Tam Richard.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved May 15, 2024. Reviewer: Arriola Laura.
Approved

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.