Estimated Timeline
4 of 9 stations approved44% complete
Key Milestones
Dec 2015
Permit Filed
New construction permit filed with DBI
Dec 2015
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2016
Dormant Period
No plan-check activity for ~73 months — applicant-side pause, not city queue time.
Aug 2024
Currently Dormant
No plan-check activity for 752 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 30 mo · Applicant: 0 mo · Dormant: 98 mo
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on August 05, 2024. 2 round(s) of review. Reviewer: Stacy Sara.
Public Health (HEALTH)
Dept. of Public Health
Comments issued on May 15, 2024. 1 round(s) of review. Reviewer: Chen Bill.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Samonsky Ella.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Guzman Miguel.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Fire (SFFD)
SF Fire Department
Approved July 05, 2024. Reviewer: Ziegler Erik.
Building Code (BLDG)
Dept. of Building Inspection
Approved March 29, 2024. Reviewer: Mcelroy Carey.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved April 11, 2024. Reviewer: Tam Richard.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved May 15, 2024. Reviewer: Arriola Laura.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.