Estimated Timeline
Permit issued — plan check completeOctober 05, 2020
Key Milestones
Apr 2016
Permit Filed
New construction permit filed with DBI
Apr 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2017
Dormant Period
No plan-check activity for ~17 months — applicant-side pause, not city queue time.
Sep 2018
Dormant Period
No plan-check activity for ~24 months — applicant-side pause, not city queue time.
Oct 2020
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 13 mo · Applicant: 0 mo · Dormant: 41 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Le Thomas.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Eng Amy.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Szu-Whitney Monica.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.