Estimated Timeline
Permit issued — plan check completeAugust 31, 2021
Key Milestones
Apr 2016
Permit Filed
New construction permit filed with DBI
Apr 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2017
Dormant Period
No plan-check activity for ~17 months — applicant-side pause, not city queue time.
Sep 2018
Dormant Period
No plan-check activity for ~35 months — applicant-side pause, not city queue time.
Aug 2021
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 12 mo · Applicant: 0 mo · Dormant: 52 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Le Thomas.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: O'Keeffe Tracy.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Szu-Whitney Monica.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Walls Mark.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.