Estimated Timeline
Permit issued — plan check completeAugust 22, 2019
Key Milestones
May 2016
Permit Filed
New construction permit filed with DBI
May 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2016
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Nov 2018
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Aug 2019
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 21 mo · Applicant: 0 mo · Dormant: 18 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Ajello Hoagland Linda.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Ajello Hoagland Linda.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zhang Kayi.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Gilbraith Kathleen.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Wong Kendrick.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.