San Francisco / Western Addition / 1001 Van Ness Av

1001 Van Ness Av

215-unit 13-story residential project to erect 13 stories, no basement, type 1-a, 215 units residential care facility for the elderly, retail, parking building.

Complete215 UnitsAB 2011 MinisterialDBI Valuation $93.6M
Entitlement
Plan Check
Jan 2020
Awaiting Issuance
Jan 2020
Post-Issuance Addenda
Construction
Dec 2021
Complete
Dec 2021
Permit Filed
Jul 2016
Time in Active Review
16 months
excludes 26 months dormant
Completed
Dec 2021
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

January 2020

Permit issued on January 02, 2020. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeJanuary 02, 2020
Key Milestones
Jul 2016
Permit Filed
New construction permit filed with DBI
Jul 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2016
Dormant Period
No plan-check activity for ~26 months — applicant-side pause, not city queue time.
Jan 2020
Permit Issued
Construction can begin
Dec 2021
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Jan 2023
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 16 mo · Applicant: 0 mo · Dormant: 26 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Woods Mary.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Mcelroy Carey.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Kreuscher Daniel.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Sep 2021
Construction startedApr 2020
Total inspections119
208 of 215 units certified for occupancy (Initial TCO, Dec 2021).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2023-01-13
106FINAL INSPECT/APPRVDPASSED
2022-02-10
142PRE-FINAL
2021-12-06
142PRE-FINAL
2021-12-03
111SITE VERIFICATION
2021-12-01
142PRE-FINAL
2021-11-30
142PRE-FINAL
2021-11-29
111SITE VERIFICATIONPASSED
2021-11-29
142PRE-FINALPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.