Estimated Timeline
Permit issued — plan check completeJanuary 02, 2020
Key Milestones
Jul 2016
Permit Filed
New construction permit filed with DBI
Jul 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2016
Dormant Period
No plan-check activity for ~26 months — applicant-side pause, not city queue time.
Jan 2020
Permit Issued
Construction can begin
Dec 2021
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Jan 2023
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 16 mo · Applicant: 0 mo · Dormant: 26 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Woods Mary.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Mcelroy Carey.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Kreuscher Daniel.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Sep 2021
208 of 215 units certified for occupancy (Initial TCO, Dec 2021).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2023-01-13
106FINAL INSPECT/APPRVDPASSED
2022-02-10
142PRE-FINAL
2021-12-06
142PRE-FINAL
2021-12-03
111SITE VERIFICATION
2021-12-01
142PRE-FINAL
2021-11-30
142PRE-FINAL
2021-11-29
111SITE VERIFICATIONPASSED
2021-11-29
142PRE-FINALPASSED