San Francisco / Western Addition / 1001 Van Ness Av

1001 Van Ness Av

215-unit 13-story residential project to erect 13 stories, no basement, type 1-a, 215 units residential care facility for the elderly, retail, parking building.

Construction Complete215 UnitsAB 2011 Ministerial$93.6M Est. Cost
Permit Filed
Jul 2016
Active Review Since
Jul 2016
Review Stations
0 of 6
stations approved
Project Status
Complete
Estimated Timeline

Permit Issued

January 2020

Permit issued on January 02, 2020. Project moved into construction phase.

Actual permit issuance date from DBI records
0 of 6 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Woods Mary.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Mcelroy Carey.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Kreuscher Daniel.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Key Milestones
Jul 2016
Permit Filed
New construction permit filed with DBI
Jul 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2020
Permit Issued
Construction can begin
Jan 2023
Construction Complete
Certificate of occupancy issued
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.