Estimated Timeline
Permit issued — plan check completeDecember 07, 2018
Key Milestones
Jul 2016
Permit Filed
New construction permit filed with DBI
Aug 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2016
Dormant Period
No plan-check activity for ~10 months — applicant-side pause, not city queue time.
Jan 2018
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
Dec 2018
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 8 mo · Applicant: 2 mo · Dormant: 19 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Sucre Richard.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Yau Willy Hoi-C.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Cheung Janice.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Yu Eric.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.