Estimated Timeline
2 of 7 stations approved28% complete
Key Milestones
Sep 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2016
Permit Filed
New construction permit filed with DBI
Nov 2016
Dormant Period
No plan-check activity for ~67 months — applicant-side pause, not city queue time.
Aug 2022
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Nov 2023
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Sep 2024
Currently Dormant
No plan-check activity for 714 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 5 mo · Applicant: 4 mo · Dormant: 111 mo
Planning (CP-ZOC)
SF Planning Department
Comments issued on August 19, 2022. 2 round(s) of review. Reviewer: Woods Mary.
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on November 10, 2023. 1 round(s) of review. Reviewer: Mcelroy Carey.
Fire (SFFD)
SF Fire Department
Comments issued on August 30, 2024. 1 round(s) of review. Reviewer: Tolentino Neil.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on September 12, 2024. 1 round(s) of review. Reviewer: Chung Diana.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved September 05, 2024. Reviewer: Choy Clinton.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved September 05, 2024. Reviewer: Mautner Allegra.
Bottleneck Watch: Planning