Estimated Timeline
2 of 7 stations approved28% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Comments issued on August 19, 2022. 2 round(s) of review. Reviewer: Woods Mary.
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on November 10, 2023. 1 round(s) of review. Reviewer: Mcelroy Carey.
Fire (SFFD)
SF Fire Department
Comments issued on August 30, 2024. 1 round(s) of review. Reviewer: Tolentino Neil.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on September 12, 2024. 1 round(s) of review. Reviewer: Chung Diana.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved September 05, 2024. Reviewer: Choy Clinton.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved September 05, 2024. Reviewer: Mautner Allegra.
Bottleneck Watch: Planning
Planning currently has open comments after 2 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.
Key Milestones
Sep 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2016
Permit Filed
New construction permit filed with DBI
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.