San Francisco / Marina / 2101 Lombard St

2101 Lombard St

9-unit 4-story residential project project proposes demolition of an existing (1) story formula retail restaurant

Dormant9 UnitsAB 2011 MinisterialDBI Valuation $2.5M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: Dormant — no activity for 180+ days. City desk: 1 mo · Applicant: 0 mo
Permit Filed
Oct 2016
Time in Active Review
1 month
excludes 54 months dormant
Review Stations
0 of 5
stations approved
Project Status
Dormant
Estimated Timeline

Permit Issuance Estimate

March 2027 — July 2028

No active review activity yet — estimate falls back to median durations for comparable SF projects of this size.

V0 empirical baselines from 5 unapproved stations
0 of 5 stations approved0% complete
Key Milestones
Oct 2016
Permit Filed
New construction permit filed with DBI
Oct 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2016
Dormant Period
No plan-check activity for ~54 months — applicant-side pause, not city queue time.
Apr 2021
Currently Dormant
No plan-check activity for 1953 days so far — applicant-side pause, not city queue time.
Mar 2027 – Jul 2028
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 1 mo · Applicant: 0 mo · Dormant: 118 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Not yet routed to this station.
Not Yet Routed
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Not Yet Routed
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Not Yet Routed

Bottleneck Watch: Building Code

Building Code has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.