Estimated Timeline
Permit issued — plan check completeMay 14, 2020
Key Milestones
Oct 2016
Permit Filed
New construction permit filed with DBI
Oct 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2016
Dormant Period
No plan-check activity for ~19 months — applicant-side pause, not city queue time.
Jun 2018
Dormant Period
No plan-check activity for ~16 months — applicant-side pause, not city queue time.
May 2020
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 9 mo · Applicant: 0 mo · Dormant: 34 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Ajello Laura.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Harshman Kjell.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Garcia Jobel.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.