San Francisco / Hayes Valley / 1740 Market St

1740 Market St

100-unit 9-story residential project to erect 9 stories of 100 dwelling units--8 stories r-2 over one story commercial

Permit Unbuilt100 UnitsAB 2011 MinisterialDBI Valuation $15.0M
Entitlement
Plan Check
Dec 2018
Awaiting Issuance
Dec 2018
Post-Issuance Addenda
Construction
Complete
Permit Filed
Oct 2016
Time in Active Review
25 months
Permit Issued
Dec 2018
plan check complete
Project Status
Permit Unbuilt
Estimated Timeline

Permit Issued

Verified never built: 1940-era 2-story commercial building still standing; retail space actively listed for lease (PropertyShark/LoopNet).

Web-verified real-world status (status_verifications.json)
Permit issued — plan check completeDecember 05, 2018
Key Milestones
Oct 2016
Permit Filed
New construction permit filed with DBI
Oct 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2018
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 25 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Foster Nicholas.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Ospital Joseph.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Haney Tom.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.