Estimated Timeline
Permit issued — plan check completeFebruary 24, 2020
Key Milestones
Oct 2016
Permit Filed
New construction permit filed with DBI
Dec 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2017
Dormant Period
No plan-check activity for ~12 months — applicant-side pause, not city queue time.
Feb 2018
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Jul 2019
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Feb 2020
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 9 mo · Applicant: 0 mo · Dormant: 29 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Townes Chris.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Townes Chris.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Harshman Kjell.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Gonzaga Janalee.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.