Estimated Timeline
Permit issued — plan check completeJanuary 22, 2019
Key Milestones
Nov 2016
Permit Filed
New construction permit filed with DBI
Nov 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2016
Dormant Period
No plan-check activity for ~17 months — applicant-side pause, not city queue time.
Jan 2019
Permit Issued
Construction can begin
Jul 2021
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 8 mo · Applicant: 0 mo · Dormant: 17 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Perry Andrew.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zee Howard.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zee Howard.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Temporary Certificate of Occupancy
95% completeLatest inspection: Apr 2026
200 of 404 units certified for occupancy (Amended TCO, Dec 2021).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-04-28
145TCO ISSUEDPASSED
2026-01-29
145TCO ISSUEDPASSED
2026-01-29
145TCO ISSUED
2022-02-15
134OK TO COVERPASSED
2021-10-12
134OK TO COVERPASSED
2021-09-09
134OK TO COVERPASSED
2021-09-01
134OK TO COVERPASSED
2021-08-05
134OK TO COVERPASSED