Estimated Timeline
Permit issued — plan check completeNovember 13, 2018
Key Milestones
Dec 2016
Permit Filed
New construction permit filed with DBI
Dec 2016
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2017
Dormant Period
No plan-check activity for ~12 months — applicant-side pause, not city queue time.
Nov 2018
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 11 mo · Applicant: 0 mo · Dormant: 12 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Ajello Hoagland Linda.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Ospital Joseph.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Stumpp Fred.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Gonzaga Janalee.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Started
5% completeLatest inspection: Jul 2026
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-07-08
101START WORKPASSED
2026-07-08
101START WORK