San Francisco / Outer Mission / 5500 Mission St

5500 Mission St

13-unit 4-story residential project to erect 4 stories, no basement, type v-a, (24) unit residential care for elderly building

Permit Filed — In Plan Check13 UnitsAB 2011 Ministerial$3.5M Est. Cost
Permit Filed
Dec 2016
Active Review Since
Feb 2019
Review Stations
0 of 8
stations approved
Project Status
Filed
Estimated Timeline

Permit Issuance Estimate

May 2026 — October 2026

Timeline driven by 3 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 8 unapproved stations
0 of 8 stations approved0% complete
Plan Check Status
Fire (SFFD)
SF Fire Department
Comments issued on July 14, 2023. 1 round(s) of review. Reviewer: Rhab Boughn.
Comments Issued
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on December 24, 2024. 1 round(s) of review. Reviewer: Sanchez Federico.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on December 24, 2024. 1 round(s) of review. Reviewer: Imson Grace.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Horn Jeffrey.
In Review
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Horn Jeffrey.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Devine Theo.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Key Milestones
Dec 2016
Permit Filed
New construction permit filed with DBI
Feb 2019
Electronic Plan Review Activated
Plans distributed to all review stations
May 2026 – Oct 2026
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.