Estimated Timeline
0 of 8 stations approved0% complete
Key Milestones
Dec 2016
Permit Filed
New construction permit filed with DBI
Feb 2019
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2019
Dormant Period
No plan-check activity for ~16 months — applicant-side pause, not city queue time.
Jun 2020
Dormant Period
No plan-check activity for ~21 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Sep 2023
Dormant Period
No plan-check activity for ~15 months — applicant-side pause, not city queue time.
Dec 2024
Dormant Period
No plan-check activity for ~17 months — applicant-side pause, not city queue time.
Sep 2026 – Nov 2026
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 13 mo · Applicant: 0 mo · Dormant: 78 mo
Fire (SFFD)
SF Fire Department
Comments issued on July 14, 2023. 1 round(s) of review. Reviewer: Rhab Boughn.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on December 24, 2024. 1 round(s) of review. Reviewer: Sanchez Federico.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on December 24, 2024. 1 round(s) of review. Reviewer: Imson Grace.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Horn Jeffrey.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Horn Jeffrey.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Devine Theo.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Bottleneck Watch: Planning