Estimated Timeline
1 of 7 stations approved14% complete
Key Milestones
Dec 2016
Permit Filed
New construction permit filed with DBI
Sep 2017
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2017
Dormant Period
No plan-check activity for ~30 months — applicant-side pause, not city queue time.
Apr 2020
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Mar 2021
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Feb 2022
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Mar 2023
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
May 2024
Dormant Period
No plan-check activity for ~24 months — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 11 mo · Applicant: 0 mo · Dormant: 97 mo
Fire (SFFD)
SF Fire Department
Comments issued on January 03, 2024. 1 round(s) of review. Reviewer: Rhab Boughn.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on March 27, 2024. 1 round(s) of review. Reviewer: Bryan Ong.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on May 14, 2024. 1 round(s) of review. Reviewer: Garcia Jobel.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Huang Vivian.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved January 08, 2024. Reviewer: Guzman Miguel.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.