Estimated Timeline
Permit issued — plan check completeMay 13, 2021
Key Milestones
May 2017
Permit Filed
New construction permit filed with DBI
May 2017
Electronic Plan Review Activated
Plans distributed to all review stations
May 2017
Dormant Period
No plan-check activity for ~30 months — applicant-side pause, not city queue time.
Apr 2020
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
May 2021
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 11 mo · Applicant: 0 mo · Dormant: 37 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Dito Matthew.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Pang David.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Gilbraith Kathleen.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Nguyen James.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.