Estimated Timeline
1 of 6 stations approved16% complete
Key Milestones
May 2017
Permit Filed
New construction permit filed with DBI
May 2017
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2017
Dormant Period
No plan-check activity for ~40 months — applicant-side pause, not city queue time.
Oct 2020
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Oct 2020
Dormant Period
No plan-check activity for ~34 months — applicant-side pause, not city queue time.
Aug 2023
Currently Dormant
No plan-check activity for 1093 days so far — applicant-side pause, not city queue time.
Apr 2027 – Oct 2028
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 1 mo · Applicant: 0 mo · Dormant: 110 mo
Building Code (BLDG)
Dept. of Building Inspection
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Public Health (HEALTH)
Dept. of Public Health
Not yet routed to this station.
Fire (SFFD)
SF Fire Department
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Planning (CP-ZOC)
SF Planning Department
Approved October 15, 2020. Reviewer: Woods Mary.
Bottleneck Watch: Fire
Fire has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.