Estimated Timeline
2 of 6 stations approved33% complete
Key Milestones
May 2017
Permit Filed
New construction permit filed with DBI
May 2017
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2017
Dormant Period
No plan-check activity for ~28 months — applicant-side pause, not city queue time.
Oct 2019
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
May 2020
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
Apr 2021
Dormant Period
No plan-check activity for ~26 months — applicant-side pause, not city queue time.
Dec 2023
Currently Dormant
No plan-check activity for 986 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 10 mo · Applicant: 0 mo · Dormant: 102 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Zhou Andy.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Building Code (BLDG)
Dept. of Building Inspection
Approved August 03, 2023. Reviewer: Mcelroy Carey.
Fire (SFFD)
SF Fire Department
Approved December 15, 2023. Reviewer: Estrella Jerry.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.