Estimated Timeline
Permit issued — plan check completeDecember 07, 2018
Key Milestones
Jul 2017
Permit Filed
New construction permit filed with DBI
Jul 2017
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2018
Permit Issued
Construction can begin
Jan 2022
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
May 2022
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 16 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Boudreaux Marcelle.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 4 cycle(s) to date. Reviewer: Chun Robert.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Cheung Janice.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Apr 2022
193 of 186 units certified for occupancy (Initial TCO, Jan 2022).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2022-05-05
106FINAL INSPECT/APPRVDPASSED
2022-04-28
142PRE-FINALPASSED
2021-12-29
111SITE VERIFICATION
2021-12-28
111SITE VERIFICATION
2021-12-27
111SITE VERIFICATION
2021-12-08
142PRE-FINALPASSED
2021-11-30
142PRE-FINALPASSED
2021-11-18
142PRE-FINALPASSED