Estimated Timeline
0 of 6 stations approved0% complete
Key Milestones
Jul 2017
Permit Filed
New construction permit filed with DBI
Jul 2017
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2017
Dormant Period
No plan-check activity for ~21 months — applicant-side pause, not city queue time.
Sep 2019
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Feb 2021
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Dec 2021
Dormant Period
No plan-check activity for ~32 months — applicant-side pause, not city queue time.
Aug 2024
Currently Dormant
No plan-check activity for 755 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 12 mo · Applicant: 0 mo · Dormant: 97 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Perry Andrew.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Jones David.
Fire (SFFD)
SF Fire Department
Currently in review. 4 cycle(s) to date. Reviewer: Harshman Kjell.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 3 cycle(s) to date. Reviewer: Kevin Li.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Fong Jeffrey.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.