San Francisco / Financial District/South Beach / 735 Davis St

735 Davis St

53-unit 6-story residential project 100% affordable housing

Complete53 UnitsAB 2011 MinisterialDBI Valuation $15.1M
Entitlement
Plan Check
Dec 2018
Awaiting Issuance
Dec 2018
Post-Issuance Addenda
Construction
Dec 2020
Complete
Dec 2020
Permit Filed
Nov 2017
Time in Active Review
7 months
excludes 6 months dormant
Completed
Dec 2020
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

December 2018

Permit issued on December 11, 2018. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeDecember 11, 2018
Key Milestones
Nov 2017
Permit Filed
New construction permit filed with DBI
Nov 2017
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2018
Dormant Period
No plan-check activity for ~6 months — applicant-side pause, not city queue time.
Dec 2018
Permit Issued
Construction can begin
Dec 2020
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Jul 2021
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 6 mo · Applicant: 1 mo · Dormant: 6 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Alexander Christy.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Zee Howard.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Yu Eric.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Chin Jeff.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Chung Diana.
In Review
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Ossai Joseph.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Dec 2020
Construction startedJun 2019
Total inspections142
53 of 53 units certified for occupancy (Initial TCO, Dec 2020).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2021-07-30
106FINAL INSPECT/APPRVDPASSED
2021-07-26
111SITE VERIFICATIONPASSED
2021-07-20
111SITE VERIFICATIONPASSED
2021-02-04
148OTHER
2020-12-31
111SITE VERIFICATIONPASSED
2020-12-28
148OTHER
2020-12-24
134OK TO COVERPASSED
2020-12-22
134OK TO COVERPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.