Estimated Timeline
Permit issued — plan check completeDecember 28, 2018
Key Milestones
Dec 2017
Permit Filed
New construction permit filed with DBI
Dec 2017
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2018
Permit Issued
Construction can begin
Oct 2022
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Mar 2023
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 12 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Alexander Christy.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Ospital Joseph.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Dec 2022
105 of 108 units certified for occupancy (Amended TCO, Oct 2022).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2023-03-10
106FINAL INSPECT/APPRVDPASSED
2023-02-06
106FINAL INSPECT/APPRVDPASSED
2022-12-23
145TCO ISSUEDPASSED
2022-12-12
142PRE-FINALPASSED
2022-10-21
145TCO ISSUEDPASSED
2022-10-19
142PRE-FINAL
2022-10-06
145TCO ISSUEDPASSED
2022-10-03
142PRE-FINALPASSED