San Francisco / Tenderloin / 500 Turk St

500 Turk St

108-unit 8-story residential project to erect 8 stories, no basement, type i-a,108 units residential with commerical/retail mixed used (r-2,m)

Complete108 UnitsAB 2011 MinisterialDBI Valuation $40.0M
Entitlement
Plan Check
Dec 2018
Awaiting Issuance
Dec 2018
Post-Issuance Addenda
Construction
Oct 2022
Complete
Oct 2022
Permit Filed
Dec 2017
Time in Active Review
12 months
Completed
Oct 2022
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

December 2018

Permit issued on December 28, 2018. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeDecember 28, 2018
Key Milestones
Dec 2017
Permit Filed
New construction permit filed with DBI
Dec 2017
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2018
Permit Issued
Construction can begin
Oct 2022
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Mar 2023
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 12 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Alexander Christy.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Ospital Joseph.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Dec 2022
Construction startedJun 2020
Total inspections62
105 of 108 units certified for occupancy (Amended TCO, Oct 2022).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2023-03-10
106FINAL INSPECT/APPRVDPASSED
2023-02-06
106FINAL INSPECT/APPRVDPASSED
2022-12-23
145TCO ISSUEDPASSED
2022-12-12
142PRE-FINALPASSED
2022-10-21
145TCO ISSUEDPASSED
2022-10-19
142PRE-FINAL
2022-10-06
145TCO ISSUEDPASSED
2022-10-03
142PRE-FINALPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.