Estimated Timeline
Permit issued — plan check completeJanuary 18, 2019
Key Milestones
Dec 2017
Permit Filed
New construction permit filed with DBI
Dec 2017
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2019
Permit Issued
Construction can begin
Mar 2021
Construction Complete
Certificate of occupancy issued
Mar 2021
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Mar 2021
Certificate of Final Completion
CFC issued — all construction obligations met.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 13 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Woods Mary.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Lau (Nelson) Chi Chiu.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Stumpp Fred.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Yu Eric.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Jan 2021
55 of 55 units certified for occupancy (CFC, Mar 2021).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2021-03-10
106FINAL INSPECT/APPRVDPASSED
2021-03-05
111SITE VERIFICATIONFAILED
2021-03-03
111SITE VERIFICATIONPASSED
2021-02-11
111SITE VERIFICATIONPASSED
2021-02-05
111SITE VERIFICATIONPASSED
2021-01-29
111SITE VERIFICATIONPASSED
2021-01-19
111SITE VERIFICATIONPASSED
2021-01-14
111SITE VERIFICATIONPASSED