San Francisco / Bernal Heights / 3310 Mission St

3310 Mission St

8-unit 5-story residential project to erect 5 stories,1 basement, type 3-a, 8 dwelling unit residential, retail with parking (r-2, m, s-2)

Complete8 UnitsAB 2011 MinisterialDBI Valuation $3.2M
Entitlement
Plan Check
Apr 2019
Awaiting Issuance
Apr 2019
Post-Issuance Addenda
Construction
Apr 2022
Complete
Apr 2022
Permit Filed
Dec 2017
Time in Active Review
16 months
Completed
Apr 2022
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

April 2019

Permit issued on April 17, 2019. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeApril 17, 2019
Key Milestones
Dec 2017
Permit Filed
New construction permit filed with DBI
Dec 2017
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2019
Permit Issued
Construction can begin
Apr 2022
Construction Complete
Certificate of occupancy issued
Apr 2022
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Apr 2022
Certificate of Final Completion
CFC issued — all construction obligations met.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 16 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Sucre Richard.
In Review
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Vu Doug.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Yu Cyril.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 3 cycle(s) to date. Reviewer: Cupido Ron.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Quan Sue.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Wong Kendrick.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Mar 2022
Construction startedDec 2019
Total inspections26
8 of 8 units certified for occupancy (CFC, Apr 2022).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2022-04-14
106FINAL INSPECT/APPRVDPASSED
2022-03-18
142PRE-FINALPASSED
2022-03-10
142PRE-FINAL
2022-03-02
142PRE-FINALPASSED
2021-01-20
134OK TO COVERPASSED
2020-11-05
135SHEETROCK NAILINGPASSED
2020-10-30
135SHEETROCK NAILINGPASSED
2020-10-27
135SHEETROCK NAILINGPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.