Estimated Timeline
Permit issued — plan check completeMarch 08, 2022
Key Milestones
Dec 2017
Permit Filed
New construction permit filed with DBI
Jan 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2018
Dormant Period
No plan-check activity for ~25 months — applicant-side pause, not city queue time.
Mar 2022
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 25 mo · Applicant: 0 mo · Dormant: 25 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 4 cycle(s) to date. Reviewer: May Christopher.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: May Christopher.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Huang Vivian.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 4 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 4 cycle(s) to date. Reviewer: Garcia Jobel.
Fire (SFFD)
SF Fire Department
Currently in review. 4 cycle(s) to date. Reviewer: Harshman Kjell.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.