San Francisco / Bayview Hunters Point / 89 Harney Wy

89 Harney Wy

124-unit 7-story residential project erect 7-story multi-family residence, retail & parking

Permit Filed — In Plan Check124 UnitsAB 2011 Ministerial$60.0M Est. Cost
Permit Filed
Dec 2017
Active Review Since
Dec 2017
Review Stations
0 of 5
stations approved
Project Status
Filed
Estimated Timeline

Permit Issuance Estimate

November 2026 — May 2027

Timeline driven by 1 station with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 5 unapproved stations
0 of 5 stations approved0% complete
Plan Check Status
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on May 01, 2024. 1 round(s) of review. Reviewer: Tom Bill.
Comments Issued
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Kwok Stephen.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Quan Sue.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed

Bottleneck Watch: Building Code

Building Code is the longest-running active review station on this project.

Key Milestones
Dec 2017
Permit Filed
New construction permit filed with DBI
Dec 2017
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.