Estimated Timeline
0 of 6 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on May 04, 2023. 1 round(s) of review. Reviewer: Mcelroy Carey.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Arriola Laura.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Feb 2018
Permit Filed
New construction permit filed with DBI
Feb 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.