Estimated Timeline
1 of 8 stations approved12% complete
Plan Check Status
Fire (SFFD)
SF Fire Department
Comments issued on September 06, 2023. 2 round(s) of review. Reviewer: Estrella Jerry.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Comments issued on September 07, 2023. 4 round(s) of review. Reviewer: Devine Theo.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on September 12, 2022. 1 round(s) of review. Reviewer: Long Ian.
Public Health (HEALTH)
Dept. of Public Health
Comments issued on August 29, 2024. 1 round(s) of review. Reviewer: Casey Ryan.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Horn Jeffrey.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Not yet routed to this station.
Building Code (BLDG)
Dept. of Building Inspection
Approved June 14, 2023. Reviewer: Walls Mark.
Bottleneck Watch: Urban Forestry
Urban Forestry has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.
Key Milestones
Mar 2018
Permit Filed
New construction permit filed with DBI
Mar 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2026 – Oct 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.