Estimated Timeline
1 of 8 stations approved12% complete
Key Milestones
Mar 2018
Permit Filed
New construction permit filed with DBI
Mar 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2018
Dormant Period
No plan-check activity for ~25 months — applicant-side pause, not city queue time.
Oct 2020
Dormant Period
No plan-check activity for ~21 months — applicant-side pause, not city queue time.
Nov 2022
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Sep 2023
Dormant Period
No plan-check activity for ~12 months — applicant-side pause, not city queue time.
Aug 2024
Currently Dormant
No plan-check activity for 728 days so far — applicant-side pause, not city queue time.
Dec 2026 – Feb 2028
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 12 mo · Applicant: 1 mo · Dormant: 88 mo
Fire (SFFD)
SF Fire Department
Comments issued on September 06, 2023. 2 round(s) of review. Reviewer: Estrella Jerry.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Comments issued on September 07, 2023. 4 round(s) of review. Reviewer: Devine Theo.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on September 12, 2022. 1 round(s) of review. Reviewer: Long Ian.
Public Health (HEALTH)
Dept. of Public Health
Comments issued on August 29, 2024. 1 round(s) of review. Reviewer: Casey Ryan.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Horn Jeffrey.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Not yet routed to this station.
Building Code (BLDG)
Dept. of Building Inspection
Approved June 14, 2023. Reviewer: Walls Mark.
Bottleneck Watch: Urban Forestry
Urban Forestry has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.