San Francisco / Sunset/Parkside / 3601 Lawton St

3601 Lawton St

15-unit 5-story residential project 201803062986to erect 5 stories, 1 basement, type 1-a / v-a, 41 dwelling units mixed use/multi family,parking and community room & roof deck

Permit Filed — In Plan Check15 UnitsAB 2011 Ministerial$7.0M Est. Cost
Permit Filed
Mar 2018
Active Review Since
Mar 2018
Review Stations
1 of 8
stations approved
Project Status
Filed
Estimated Timeline

Permit Issuance Estimate

August 2026 — October 2027

Timeline driven by 4 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 7 unapproved stations
1 of 8 stations approved12% complete
Plan Check Status
Fire (SFFD)
SF Fire Department
Comments issued on September 06, 2023. 2 round(s) of review. Reviewer: Estrella Jerry.
Comments Issued
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Comments issued on September 07, 2023. 4 round(s) of review. Reviewer: Devine Theo.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on September 12, 2022. 1 round(s) of review. Reviewer: Long Ian.
Comments Issued
Public Health (HEALTH)
Dept. of Public Health
Comments issued on August 29, 2024. 1 round(s) of review. Reviewer: Casey Ryan.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Horn Jeffrey.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Not yet routed to this station.
Not Yet Routed
Building Code (BLDG)
Dept. of Building Inspection
Approved June 14, 2023. Reviewer: Walls Mark.
Approved

Bottleneck Watch: Urban Forestry

Urban Forestry has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.

Key Milestones
Mar 2018
Permit Filed
New construction permit filed with DBI
Mar 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2026 – Oct 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.