Estimated Timeline
Permit issued — plan check completeDecember 07, 2018
Key Milestones
Apr 2018
Permit Filed
New construction permit filed with DBI
Apr 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2018
Permit Issued
Construction can begin
Dec 2022
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
May 2023
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 8 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Adina Seema.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Mcelroy Carey.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Harshman Kjell.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Zhou Andy.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Mar 2023
94 of 94 units certified for occupancy (Initial TCO, Dec 2022).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2023-05-16
106FINAL INSPECT/APPRVDPASSED
2023-04-25
106FINAL INSPECT/APPRVDPASSED
2023-03-08
145TCO ISSUEDPASSED
2023-02-13
126ROUGH FRAMEPASSED
2022-12-13
145TCO ISSUEDPASSED
2022-12-12
148OTHER
2022-11-28
142PRE-FINAL
2022-10-19
142PRE-FINAL