San Francisco / Lone Mountain/USF / 709 Lyon St

709 Lyon St

5-unit 4-story residential project to erect 4 stories, 1 basement, type iii-a, 5 unit residential bldg

Complete5 UnitsAB 2011 MinisterialDBI Valuation $3.4M
Entitlement
Plan Check
Oct 2019
Awaiting Issuance
Oct 2019
Post-Issuance Addenda
Construction
Dec 2022
Complete
Dec 2022
Permit Filed
Apr 2018
Time in Active Review
7 months
excludes 11 months dormant
Completed
Dec 2022
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

October 2019

Permit issued on October 24, 2019. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeOctober 24, 2019
Key Milestones
Apr 2018
Permit Filed
New construction permit filed with DBI
Apr 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2018
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Oct 2019
Permit Issued
Construction can begin
Dec 2022
Construction Complete
Certificate of occupancy issued
Dec 2022
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Dec 2022
Certificate of Final Completion
CFC issued — all construction obligations met.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 7 mo · Applicant: 0 mo · Dormant: 11 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Jimenez Sylvia.
In Review
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Jimenez Sylvia.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Ng Joe.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Harshman Kjell.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Yu Eric.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Heller Morgan.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Dec 2021
Construction startedOct 2020
Total inspections37
5 of 5 units certified for occupancy (CFC, Dec 2022).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2022-12-01
106FINAL INSPECT/APPRVDPASSED
2022-11-23
106FINAL INSPECT/APPRVDPASSED
2022-11-18
106FINAL INSPECT/APPRVDFAILED
2022-11-18
106FINAL INSPECT/APPRVDPASSED
2021-12-06
135SHEETROCK NAILINGPASSED
2021-11-24
135SHEETROCK NAILINGPASSED
2021-11-10
135SHEETROCK NAILINGPASSED
2021-11-03
133LATH, EXTERIORFAILED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.