Estimated Timeline
0 of 6 stations approved0% complete
Key Milestones
Apr 2018
Permit Filed
New construction permit filed with DBI
Apr 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2018
Dormant Period
No plan-check activity for ~10 months — applicant-side pause, not city queue time.
Jan 2020
Dormant Period
No plan-check activity for ~6 months — applicant-side pause, not city queue time.
Aug 2020
Dormant Period
No plan-check activity for ~22 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Aug 2023
Currently Dormant
No plan-check activity for 1120 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 12 mo · Applicant: 0 mo · Dormant: 88 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Kwok Stephen.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Kwok Stephen.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.