Estimated Timeline
0 of 6 stations approved0% complete
Key Milestones
Apr 2018
Permit Filed
New construction permit filed with DBI
Apr 2018
Electronic Plan Review Activated
Plans distributed to all review stations
May 2018
Dormant Period
No plan-check activity for ~50 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Aug 2023
Currently Dormant
No plan-check activity for 1120 days so far — applicant-side pause, not city queue time.
Apr 2027 – Oct 2028
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 0 mo · Applicant: 0 mo · Dormant: 100 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date.
Building Code (BLDG)
Dept. of Building Inspection
Not yet routed to this station.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Fire (SFFD)
SF Fire Department
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Bottleneck Watch: Fire
Fire has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.