Estimated Timeline
Permit issued — plan check completeDecember 05, 2018
Key Milestones
Apr 2018
Permit Filed
New construction permit filed with DBI
Apr 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2018
Permit Issued
Construction can begin
May 2021
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Nov 2021
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 7 mo · Applicant: 1 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Vu Doug.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zee Howard.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Yu Eric.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Jun 2020
242 of 371 units certified for occupancy (Amended TCO, Jul 2021).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2021-11-30
106FINAL INSPECT/APPRVDPASSED
2021-05-19
148OTHERPASSED
2021-05-14
148OTHER
2021-05-12
148OTHERPASSED
2021-04-05
127INSULATION
2021-03-23
142PRE-FINAL
2021-03-16
127INSULATIONPASSED
2021-03-11
127INSULATIONPASSED