San Francisco / Mission / 3001 24Th St

3001 24Th St

45-unit 5-story residential project priority processing

Complete45 UnitsAB 2011 MinisterialDBI Valuation $14.7M
Entitlement
Plan Check
Mar 2019
Awaiting Issuance
Mar 2019
Post-Issuance Addenda
Construction
Jun 2021
Complete
Jun 2021
Permit Filed
Jun 2018
Time in Active Review
9 months
Completed
Jun 2021
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

March 2019

Permit issued on March 18, 2019. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeMarch 18, 2019
Key Milestones
Jun 2018
Permit Filed
New construction permit filed with DBI
Jun 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2019
Permit Issued
Construction can begin
Jun 2021
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Dec 2021
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 9 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Durandet Kimberly.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Jones David.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Chin Jeff.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Jun 2021
Construction startedApr 2020
Total inspections49
45 of 45 units certified for occupancy (Initial TCO, Jun 2021).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2021-12-16
106FINAL INSPECT/APPRVDPASSED
2021-06-23
142PRE-FINALPASSED
2021-06-22
142PRE-FINALPASSED
2021-06-21
142PRE-FINALPASSED
2021-06-03
134OK TO COVER
2021-06-02
111SITE VERIFICATIONPASSED
2021-06-01
134OK TO COVERPASSED
2021-05-13
126ROUGH FRAMEPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.