San Francisco / Visitacion Valley / 242 Hahn St

242 Hahn St

167-unit 5-story residential project priority processing

Complete167 UnitsAB 2011 MinisterialDBI Valuation $70.0M
Entitlement
Plan Check
Feb 2019
Awaiting Issuance
Feb 2019
Post-Issuance Addenda
Construction
Nov 2021
Complete
Nov 2021
Permit Filed
Jun 2018
Time in Active Review
7 months
Completed
Nov 2021
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

February 2019

Permit issued on February 15, 2019. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeFebruary 15, 2019
Key Milestones
Jun 2018
Permit Filed
New construction permit filed with DBI
Jul 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2019
Permit Issued
Construction can begin
Nov 2021
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Jun 2022
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 7 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Snyder Mathew.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Kwok Stephen.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Yu Eric.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Jun 2022
Construction startedJan 2020
Total inspections135
167 of 167 units certified for occupancy (Initial TCO, Nov 2021).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2022-06-24
106FINAL INSPECT/APPRVDPASSED
2022-06-22
106FINAL INSPECT/APPRVDFAILED
2022-06-17
142PRE-FINALPASSED
2021-10-15
142PRE-FINALPASSED
2021-10-14
142PRE-FINALPASSED
2021-10-13
142PRE-FINALPASSED
2021-10-12
142PRE-FINALPASSED
2021-10-08
142PRE-FINALPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.