Estimated Timeline
Permit issued — plan check completeFebruary 15, 2019
Key Milestones
Jun 2018
Permit Filed
New construction permit filed with DBI
Jul 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2019
Permit Issued
Construction can begin
Nov 2021
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Jun 2022
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 7 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Snyder Mathew.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Kwok Stephen.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Yu Eric.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Jun 2022
167 of 167 units certified for occupancy (Initial TCO, Nov 2021).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2022-06-24
106FINAL INSPECT/APPRVDPASSED
2022-06-22
106FINAL INSPECT/APPRVDFAILED
2022-06-17
142PRE-FINALPASSED
2021-10-15
142PRE-FINALPASSED
2021-10-14
142PRE-FINALPASSED
2021-10-13
142PRE-FINALPASSED
2021-10-12
142PRE-FINALPASSED
2021-10-08
142PRE-FINALPASSED