Estimated Timeline
Permit issued — plan check completeJanuary 31, 2019
Key Milestones
Jul 2018
Permit Filed
New construction permit filed with DBI
Jul 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2019
Permit Issued
Construction can begin
May 2023
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Jun 2024
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 7 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Horn Jeffrey.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zee Howard.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Debella Al.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Yu Eric.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: May 2023
131 of 131 units certified for occupancy (Initial TCO, May 2023).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2024-06-06
106FINAL INSPECT/APPRVDPASSED
2023-08-16
145TCO ISSUED
2023-07-12
142PRE-FINAL
2023-05-26
145TCO ISSUEDPASSED
2023-05-22
111SITE VERIFICATION
2023-05-18
142PRE-FINAL
2023-05-18
142PRE-FINALPASSED
2023-05-06
142PRE-FINAL