San Francisco / Outer Mission / 5616 Mission St

5616 Mission St

10-unit 4-story residential project erect a 4 stories,no basement, type ia,iiia, 8 dwelling multi-family with commercial/retail on 1st fl building.

Complete10 UnitsAB 2011 MinisterialDBI Valuation $1.0M
Entitlement
Plan Check
Aug 2020
Awaiting Issuance
Aug 2020
Post-Issuance Addenda
Construction
Oct 2025
Complete
Oct 2025
Permit Filed
Jul 2018
Time in Active Review
16 months
excludes 8 months dormant
Completed
Oct 2025
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

August 2020

Permit issued on August 12, 2020. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeAugust 12, 2020
Key Milestones
Jul 2018
Permit Filed
New construction permit filed with DBI
Jul 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2018
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
Aug 2020
Permit Issued
Construction can begin
Oct 2025
Construction Complete
Certificate of occupancy issued
Oct 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Oct 2025
Certificate of Final Completion
CFC issued — all construction obligations met.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 16 mo · Applicant: 0 mo · Dormant: 8 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Washington Delvin.
In Review
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Tran Nancy.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Finnegan John.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Wong Victor.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Apr 2025
Construction startedDec 2022
Total inspections29
8 of 10 units certified for occupancy (CFC, Oct 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-10-31
106FINAL INSPECT/APPRVDPASSED
2025-10-30
106FINAL INSPECT/APPRVD
2025-04-10
135SHEETROCK NAILINGPASSED
2025-04-07
132FLUES/VENTS/DUCTSPASSED
2025-03-20
135SHEETROCK NAILINGPASSED
2025-03-12
127INSULATIONPASSED
2025-01-30
126ROUGH FRAMEPASSED
2024-11-20
125ROUGH FRAME, PARTIALPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.