Estimated Timeline
Permit issued — plan check completeAugust 12, 2020
Key Milestones
Jul 2018
Permit Filed
New construction permit filed with DBI
Jul 2018
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2018
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
Aug 2020
Permit Issued
Construction can begin
Oct 2025
Construction Complete
Certificate of occupancy issued
Oct 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Oct 2025
Certificate of Final Completion
CFC issued — all construction obligations met.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 16 mo · Applicant: 0 mo · Dormant: 8 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Washington Delvin.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Tran Nancy.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Finnegan John.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Wong Victor.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Apr 2025
8 of 10 units certified for occupancy (CFC, Oct 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-10-31
106FINAL INSPECT/APPRVDPASSED
2025-10-30
106FINAL INSPECT/APPRVD
2025-04-10
135SHEETROCK NAILINGPASSED
2025-04-07
132FLUES/VENTS/DUCTSPASSED
2025-03-20
135SHEETROCK NAILINGPASSED
2025-03-12
127INSULATIONPASSED
2025-01-30
126ROUGH FRAMEPASSED
2024-11-20
125ROUGH FRAME, PARTIALPASSED